Slaptijack was offline for 2.5 hours today when the data center with our server in it experienced a power outage. Apparently, the roof started leaking during a heavy rain storm and water dropped directly on a panel controlling the UPS. This caused the UPS to shutdown, and it took 2.5 hours for the data center personnel to bypass the UPS and put all customers onto very interruptible city power. So far, there have been no more outages since power was restored, but there may be downtime when customers are moved off city power and back on to the UPS.